SP Group Solar Compliance Checks: What to Expect

Ensure your solar PV system passes SP Group’s compliance checks with this detailed guide. Learn about the inspection process, documentation requirements, and how to stay compliant under Singapore’s regulatory framework.

Table of Contents

  • What Is an SP Group Compliance Check?
  • What Do SP Inspectors Check?
  • Required Documents for Inspection
  • What to Expect on Inspection Day
  • Tips to Pass SP Compliance Smoothly

What Is an SP Group Compliance Check?

After your solar PV system is installed, SP Group (Singapore Power) will conduct a compliance check before allowing the system to be connected to the national grid. This ensures your system is safe, correctly installed, and compliant with Energy Market Authority (EMA) and SP Services regulations. The inspection typically happens after your Licensed Electrical Worker (LEW) submits the Certificate of Compliance (COC).

What Do SP Inspectors Check?

SP Group inspectors will review:

  • The proper functioning and labeling of your distribution board (DB)

  • Your inverter's wiring and isolation switches

  • The earthing of your system

  • Whether your generation meter and import/export meter are correctly set up

  • Safety clearances and accessibility of equipment

Any non-compliance or hazards may delay approval to operate your solar system.

Required Documents for Inspection

Make sure these documents are submitted and ready:

  • Certificate of Compliance (COC) from your LEW

  • Single-line diagram (SLD) of your electrical system

  • System layout plan showing location of panels, isolators, inverter

  • Product datasheets (inverter and panels)

  • Any additional documents SP Group or EMA may request based on project size or type.

Your solar installer and LEW should help prepare this packet.

What to Expect on Inspection Day

  • The inspection is usually conducted during working hours

  • An SP Group officer will inspect the system onsite, including your inverter, rooftop, and DB panel

  • You (or your installer) should ensure access to all equipment is available

  • Minor on-the-spot rectifications may be requested

  • After passing, SP will proceed to activate your export meter and system approval

Tips to Pass SP Compliance Smoothly

  • Appoint an experienced and EMA-licensed solar contractor and LEW

  • Ensure labels are printed and clearly fixed on isolators, breakers, and inverter

  • Keep your DB neat and wired according to the SLD

  • Make sure isolators are weatherproof and accessible

  • Schedule an internal check with your installer before SP’s site visit

These measures help you avoid delays and improve long-term system safety.